Rio Tinto and Rondo Start Design of a 360 MWh Heat Battery at Yarwun Refinery
Hardware / news
Rio Tinto and Rondo Start Design of a 360 MWh Heat Battery at Yarwun Refinery
A 30 MW discharge rating and a 4 to 6 hour solar window imply charging power well above 30 MW. The study is funded; construction is not.

Rio Tinto and Rondo Energy have started front-end engineering and design for a 30 MW, 360 MWh heat battery at Rio Tinto's Yarwun alumina refinery near Gladstone, Queensland, the companies announced on October 20, 2026.
The Rondo release calls it Australia's largest thermal energy storage project and says the unit would deliver heat of up to 1,000°C, mainly as steam into Yarwun's existing steam network, if the project proceeds. pv magazine Australia adds that it would be a world first for the alumina industry. Nothing has been approved for construction: the current stage is a study.

The 360 MWh and 30 MW arithmetic
Divide 360 MWh by 30 MW and the battery runs for 12 hours at full discharge. The release says the unit charges at midday from surplus solar power and discharges continuously, to supply process heat around the clock, and that Australia has about 4 to 6 hours of surplus midday solar a day.
The number that matters here is not the 30 MW discharge but the charging power it implies. Filling 360 MWh in 6 hours takes at least 60 MW of electrical input; in 4 hours, at least 90 MW, before any losses. That is our arithmetic, not a figure from either company, and it means the grid connection and the midday power supply matter as much as the bricks. Neither source gives a charging rating, a cost or a build timeline.
| Item | Figure | Source |
|---|---|---|
| Storage | 360 MWh | Rondo release |
| Discharge | 30 MW | Rondo release |
| Full-discharge duration | 12 hours | The Terminal's arithmetic |
| Heat output | Up to 1,000°C | Rondo release |
| Round-trip efficiency | Above 98% | Rondo, via pv magazine |
The efficiency figure is Rondo's own and no independent test is cited in the coverage.
Who is paying for the study
The Australian Renewable Energy Agency (ARENA) is providing $3.6 million for the engineering study, per the release, which does not name the currency. A further $38 million is available for deployment after a successful study, and up to $33.3 million of conditional contingency support covers defined risks such as cost overruns and electricity costs.
- Engineering study (committed)3.6 $ million
- Deployment (after study)38 $ million
- Contingency (conditional)33.3 $ million
Source: Rondo Energy release via PR Newswire, Oct. 20, 2026
Only the first line is committed. The other two depend on the study succeeding and on named risks materialising. The release does not state the total project cost, so the share ARENA would cover cannot be worked out from what was published.
What the companies say
Armando Torres, Rio Tinto Pacific Operations Managing Director, said the study will determine whether thermal storage is "a technically and economically viable alternative to fossil fuels" for part of Yarwun's steam requirements, according to pv magazine. Kira Rundel, Rondo's head of Australia, said in the release: "This project shows how Australia's abundant energy can become a competitive advantage for industry." Darren Miller, ARENA's chief executive, said demonstrations like this will help build the evidence industry needs for future investment decisions.
pv magazine reports the project would cut about 67,000 tonnes of carbon dioxide a year from on-site emissions if it goes ahead. That figure appears in one of the two sources we read and not in the release, so treat it as reported rather than confirmed. Neither source says what share of Yarwun's steam the battery would replace; both say only "part".
The next concrete marker is the end of the engineering study, which would unlock the $38 million deployment tranche. Neither company has said how long it will take. For other hardware where an announced capacity has yet to be matched by disclosed numbers, see our coverage of Tenstorrent's Series E and the AGCO Digit pilot.
Sources
More in Hardware
- 01Porsche Wireless Charging: 90 Percent Efficiency Is the Number to WatchAn 11 kW floor pad for the Cayenne Electric is orderable in Europe, and the five-point efficiency gap to a cable adds up to roughly 4 kWh per fast home top-up.
- 02Tesla Dates Unsupervised FSD for Owners at Q2 2027, Inside Robotaxi Zones OnlyAshok Elluswamy gave the date on the Q3 call, and Electrek reports the first version is a way to add owned cars to Tesla's managed Robotaxi fleet.
- 03Tenstorrent Raises $1.5 Billion at $6.2 Billion, 24 Percent Above Reported Takeover InterestNeither TechCrunch nor BetaKit reports a Galaxy server spec, price, customer or revenue figure for the chip maker's Series E.
- 04Boston Dynamics' New Atlas Hand Has 13 Actuators and a 100,000-a-Year Target, but No Cost FigureThe company's Oct. 1 announcement dropped the pinky and published a 100-pound carry claim, while leaving out the cost, durability and unit numbers that decide whether a hand can be mass-produced.